Timeline
Next
All dates are estimates and subject to change.
Project selected for design-only funding through MSTIP 3e
October 2016
Design starts
September 2022
Design paused while funding is reevaluated
January-June 2024
60% of design completed
November 2024
Open house
Nov. 22-Dec. 8, 2024
You are here.
Final design
December 2024-January 2026
Right-of-way acquisition
March 2025-January 2026
Construction
Spring 2026-Fall 2027