All dates are estimates and subject to change.

 
  • Project selected for design-only funding through MSTIP 3e

    October 2016
  • Design starts

    September 2022
  • Design paused while funding is reevaluated

    January-June 2024
  • 60% of design completed

    November 2024
  • Open house

    Nov. 22-Dec. 8, 2024

    You are here.

  • Final design

    December 2024-January 2026
  • Right-of-way acquisition

    March 2025-January 2026
  • Construction

    Spring 2026-Fall 2027